Putting the dataset into the acceptance sheet: three November documents, three new handover lines

The short version: three public documents published in November all moved the conversation from "build a system" to "can the data be re-checked, and can you explain what the agent did". We updated three lines of our smart-factory handover checklist accordingly — in the acceptance sheet, not as an optional line in a proposal, because optional lines are the first to disappear when a schedule tightens.

This is not a new service and does not represent any rating, certification or listing. It is a change to deliverables: acceptance items the client already signs off on are now written so they can be checked line by line against public documents. Here is what changed, why, and what a client needs to prepare.

1. What each of the three documents actually said

The three have different status (a ministerial notice, conference figures, a provincial action plan) and should not be read as one. We only quote the sentence that bears on handover and acceptance.

DocumentDate / sourceThe line that matters for deliveryStatus
2026 pioneering-grade smart factory cultivation list notice
Joint notice by six ministries, MIIT letter [2026] No. 562
17 Nov 2026
MIIT official site
Guide the building of high-quality datasets, develop industrial agents, explore advanced manufacturing models and build smart supply chainsMinisterial notice; official text governs
2026 China 5G + Industrial Internet Conference
18–20 Nov, Wuhan
19 Nov 2026
China News Service
Release the value of industrial data factors faster; support platform firms in building large, high-quality, tradable sector datasets for high-value scenariosConference figures, press reporting
Manufacturing digital transformation / industrial internet platform action plans
Provincial plans, 2026–2028
Issued 4 Nov 2026
reported 12 Nov
Organise scenarios with "one map, four lists"; cultivate low-cost, easy-to-deploy standard products and "platform + agent" offerings for SMEsProvincial scope, not a national conclusion
What the three share is not "adopt AI" but turning data definitions, scenario lists and action boundaries into things that can be checked. That is exactly what a handover sheet is for.
Notice 562 · 17 Novdatasets / industrial agents 5G+IIoT conference · 19 Novtradable sector datasets Provincial plan · 4 Novone map, four lists Handover sheet · 3 lines 1. Dataset spec is re-checkable 2. Agent actions have boundaries 3. Acceptance by sample recompute all three land in the signed sheet Client can verify named owner / human sign-off one recomputable sample
Three documents → three acceptance lines → a deliverable the client can verify; left box is a summary of public documents, right box is our delivery action

2. The three lines we changed

Acceptance itemBeforeNowClient prepares
Dataset specificationA database dictionaryCapture-point list + field definitions + missing/outlier handling rules + sample time window; all four requiredA business owner for every field who can explain its definition
Agent action boundariesNot presentA read-only / write action list, the human sign-off point for each write class, and audit fields (who initiated, which rows, on what evidence)Which actions must never be auto-submitted
Acceptance methodFeature-by-feature demoPlus one recomputable sample: from raw capture values to the dashboard figure, the client reaches the same number independentlyA sample dataset with no sensitive data and an expected result

All three are about writing things down, not adding a feature. For live systems we update documents through the change process without touching production data; for new projects the lines go into the contract annex. It is the same habit as always: a delivery boundary on paper is more reliable than one in a demo.

3. Why the acceptance sheet, not a proposal option

  • Optional lines get cut first. When a schedule tightens, work that produces no screen — data definitions, for instance — is the first to go, yet it is the ground for every later reconciliation and report.
  • A sheet is checkable by both sides. A demo is led by the vendor; a sample recompute is led by the client. Handing part of acceptance back reduces disputes.
  • Public documents "guide" and "support"; they do not certify. Our job is to translate guidance into signable items, not to issue a verdict on behalf of any review body.

4. What these three lines do not promise

  1. No rating, recognition or subsidy outcome. Cultivation lists and city-pilot awards have their own application and review processes; official texts and competent authorities govern.
  2. A provincial plan is not a national requirement. The third document is provincial and its "by 2028" figures are targets, not current statistics; they cannot be compared directly with counted figures elsewhere.
  3. No new charge item. The three lines refine existing deliverables and go through the change process; we do not open a new line because a policy became topical.

If you are scoping or accepting a smart-factory project, two things make the conversation fast: the current field list, and the actions you want a human to sign.

Sources and caveats

  • MIIT and five other ministries, notice on the 2026 pioneering-grade smart factory cultivation list (MIIT letter [2026] No. 562), 17 Nov 2026, MIIT official site; official text governs.
  • 2026 China 5G + Industrial Internet Conference figures, China News Service, 19 Nov 2026 (Wuhan, 18–20 Nov); press reporting.
  • Provincial manufacturing digital-transformation and industrial-internet platform action plans (2026–2028), issued 4 Nov 2026, reported 12 Nov 2026; provincial, target figures.
Written from public information as a description of method and delivery. Policy and figures come from official texts or press reporting; they do not mean Jiding Technology has taken on related projects, joined any list or obtained any recognition. Figures from different bodies, definitions and dates are not directly comparable; official texts govern. No client information, pricing or promises are included.