The short version: this month we delivered two systems for the same made-to-order equipment factory: a browser-based production monitoring back office and an Android shop-floor app carried by line foremen. They are not two halves of one project — the back office is where documents and stock live, the app is where actions and photos happen, and one work-order number holds them together. This note records how the two delivery lines differed and what went into the handover package.
1. Why two, not one
The first requirement sheet said "one system". After a day on the shop floor we found the office and the floor run on different clocks: the office waits for data, the floor races through actions. Forcing foremen into a browser and planners into a twenty-screen mobile app both fight human nature.
So the plan became two entrances on one data foundation: drawing breakdown, shortage-to-purchase, receipts and issues, the eight stock actions and permissions stay in the back office; reporting, QC photos, picking and approvals live in the app. No data is built twice — documents created in the back office are pushed to the app for execution, and app records write back against the same order.
The full function sets are described in the monitoring case study and the app case study; this note only records the delivery itself.
2. Two delivery lines, two rhythms
| PC back office | Shop-floor app | |
|---|---|---|
| Users | Planning, purchasing, warehouse, QC, management | Foremen, operators, QC inspectors |
| Change source | Process rules: document flow, permissions, report definitions | Floor habits: field order, button size, photo angles |
| Acceptance | Walk the document-flow diagram line by line | Three shifts, real devices, one week each |
| Most rework | How one shortage splits into two purchase orders | Submission and resume under weak signal |
| Go-live order | First — stand up the document foundation | Second — act on documents that already flow |
Rework logs confirm it: back-office rework concentrated on "rules not aligned" — how order numbers inherit when a shortage splits; app rework concentrated on "habits not aligned" — veterans photograph first and count later, so the form order had to change. Rules can be settled in a meeting; habits can only be learned on the floor.
3. Three things that joined the handover package
- Weak-signal checklist: dead corners in a workshop are the norm. App submissions now always use local staging with retransmission, and acceptance includes standing at the worst-covered workstation. It is now part of our app acceptance standard.
- Number-inheritance map: every delivery includes a diagram of how document numbers inherit (shortage → purchase → receipt → pick) and what happens on gaps. Clients extend it when they add document types.
- Two-entrance permission table: the same person's rights in both entrances must match. Back-office roles and app roles now ship as one cross-reference table, ending "has rights on desktop, button greyed out on mobile" arguments.
Together with the added after last month's health check, the handover package has grown a lot this year — all of it paid for by real projects.
4. Three suggestions for factories starting the same journey
- Run the back-office document flow first, then ship the app. Actions need documents to attach to. An app before the foundation means two sets of books.
- Accept the app in the workshop, never in a meeting room. Full Wi-Fi, good light and free people make everything pass; the floor is not like that.
- Unify accounts across both entrances on day one. Merging account systems afterwards costs ten times the design.